B. Demonstrate complete system operations for District Engineer or Project Manager prior<br />

to system acceptance.<br />

C. Training<br />

1. Perform training at the same time as commissioning is done. Utilize specific<br />

manuals and record documentation.<br />

2. provide eight (8) hour training session for BMCS covering following topics:<br />

a. Sequence of operation review<br />

b. Use of operator’s terminal<br />

c. Operating time schedules<br />

d. Alarm messages<br />

e. Network communications, both local and within the district’s LAN.<br />

f. Review modifying setpoints and schedules<br />

g. Questions and answers.<br />

C. Final Acceptance<br />

1. Written acceptance sign-off of system operation will then occur after<br />

commissioning and training are complete. Acceptance will be signed by District’s<br />

designated Commissioning Agent<br />

2. Checklist, provided by District, shall be initialed and signed by District’s Project<br />

Manager at completion.<br />

a. Punch list items completed and BMCS accepted.<br />

b. Checklist shall verify required training has been provided.<br />

c. Checklist shall also be signed by BMCS trainer and forwarded to<br />

District Engineer for final review and approval<br />

d. Final payment will not be made until checklist has been received,<br />

reviewed and approved by District’s Engineer.<br />

SEGO LILY ELEMENTARY SCHOOL CLASSROOM ADDITION<br />

AUTOMATIC TEMPERATURE CONTROLS 15900-27