AIR HANDLING UNIT: (AHU-1)<br />

Part 1 — General<br />

1.01 QUALITY ASSURANCE<br />

A. Manufacturer Qualifications:<br />

Company specializing in manufacturing the products specified in this section with minimum of five<br />

years documented experience.<br />

B. Units shall be manufactured in a facility registered to ISO 9001:2000 manufacturing quality standard.<br />

C. Air-handling unit assembly shall have UL 1995 certification for safety.<br />

D. Coil performance shall be certified in accordance with ARI Standard 410.<br />

E. Air-handling unit shall be ARI 430 listed and meet NFPA 90A requirements.<br />

1.02 DELIVERY, STORAGE AND PROTECTION<br />

A. All indoor units, painted or unpainted, shall be completely shrink-wrapped from the factory for<br />

protection during shipment. Tarping of bare units is unacceptable.<br />

B. Inspect for transportation damage and store in clean dry place and protect from weather and<br />

construction traffic. Handle carefully to avoid damage to components, enclosures, and finish.<br />

1.03 START-UP REQUIREMENTS<br />

Do not operate units until ductwork is clean, filters are in place, bearings lubricated, condensate properly<br />

trapped, piping connections verified and leak tested, belts aligned and tensioned, all shipping braces<br />

have been removed, and fan has been test run under observation.<br />

Part 2 — Products<br />

2.01 GENERAL DESCRIPTION<br />

A. Units shall ship in the number of sections necessary to meet project requirements.<br />

B. Unit shall be factory-supplied, central station air handler. The air-handling unit shall consist of a fan<br />

with the following factory-installed components as indicated on the equipment schedule.<br />

1. Filter/Mixing Box Section including outside air dampers, return air dampers, filter racks, filter<br />

access door, and filters (to include an additional set to be left with the owner).<br />

2. Hot water coil.<br />

3. Chilled water coil with stainless steel condenser drain pan and connection.<br />

4. Fan section with plenum fan.<br />

.<br />

2.02 CASING<br />

A. <strong>Construction</strong>:<br />

1. Unit shall be constructed of a complete frame with easily removable panels. Removal of any<br />

panel shall not affect the structural integrity of the unit. Single height coil sections shall have<br />

removable frame sections to facilitate vertical coil extraction.<br />

2. All units shall be supplied with 16-gage, G-90 galvanized steel base rails. Bolt-on legs are<br />

NOT acceptable. Perimeter 10-gage lifting lugs for overhead lifting shall be provided on each<br />

section. Slinging units in place of lifting lugs shall not be acceptable.<br />

3. Unit shall be thermally broken to minimize the conduction path from the inside of the casing<br />

to the outside.<br />

4. Casing panels (top, sides, and bottom) shall be constructed of galvanized steel, and shall<br />

have one of the following exterior finishes as specified:<br />

a. Pre-painted with a baked enamel finish passing 500-hour salt spray test (ASTM B-117) for<br />

____________________________________________________________________________________________________________________________________________________________________________________<br />

____<br />

SEGO LILY ELEMENTARY SCHOOL CLASSROOM ADDITION March 2, 2009<br />

HEATING-COOLING 15700-8