1. Strainers and filters.<br />

2. Visual check of air flow for "best guess" setting for preparation for system air balancing under Section<br />

15043.<br />

3. Control operation of time clocks, on-off sequences, system cycling, etc.<br />

4. Visual checks for water flow, seals, packings, safety valves, operating pressures and temperatures.<br />

5. Cleaning of excessive oil or grease.<br />

6. Dampers close tightly.<br />

7. Valves close tightly.<br />

8. System leaks.<br />

9. All other items pertaining to the proper operation of the mechanical system, whether specifically listed or<br />

not.<br />

WARRANTY SCHEDULE:<br />

Provide a list in each O & M Manual of all motors, fans, and equipment with manufacturer's names, models,<br />

serial numbers and date of startup approved by the Owner's representative, date of warranty, extent of warranty,<br />

and equipment supplier with address and phone numbers.<br />

SCHEDULE OF OVERLOAD PROTECTION:<br />

Provide a list in each O & M Manual of all motors with size, voltage, amperage, and size and rating of overload<br />

protection.<br />

REPORT:<br />

Prior to the start of system balancing the system commissioning sub-contractor shall submit a written report to<br />

the owner's representative outlining the results of the system commissioning work for each system and piece of<br />

equipment which lists any un-corrected system abnormalities. This report is mandatory.<br />

CERTIFICATION:<br />

Provide written certification of all tests, and start-up procedures. Bind a copy of this certification in the O & M<br />

manuals. Certification shall include an itemized list of systems serviced during the system commissioning<br />

process with dates, times, and a complete description of the work completed, and the name of responsible<br />

system commissioning mechanic.<br />

________________________________________________________________________________________________________________________________________________________________________________<br />

_______<br />

SEGO LILY ELEMENTARY SCHOOL CLASSROOM ADDITION March 2, 2009<br />

SYSTEM COMMISSIONING 15030-3