SECTION 15042 - TESTING<br />

PART 1.00 - GENERAL<br />

DESCRIPTION:<br />

The work outlined in this section shall be performed by the several trades involved.<br />

The mechanical contractor shall provide all supervision, labor, materials, tools, scaffolding, and equipment<br />

required to complete all system testing.<br />

The mechanical contractor shall remove and repair any defective component as indicated by the system<br />

tests and retest.<br />

The mechanical contractor shall test the operation of all safety and high limit controls to insure proper<br />

installation and operation. Any defective devices shall be replaced.<br />

TESTS AND ADJUSTMENTS:<br />

Before any piping is covered, tests shall be made in the presence of the Owner's Representative, and any<br />

leaks or defective work corrected. No caulking of threaded work will be permitted.<br />

Before application of insulation covering, and as far as practical before concealing any piping, all piping shall<br />

be hydrostatically tested and proved tight.<br />

Stubs shall be capped and all control valves shall be removed during the test.<br />

System may be tested in sections, providing connections to last section tested are included in each<br />

succeeding test.<br />

Following minimum pressures shall be used for testing:<br />

1. Domestic hot, cold, and hot water recirculating water piping at 150 psig for six hours.<br />

2. Refrigeration piping, as indicated in Section "Refrigeration Piping Installation."<br />

3. Heating hot water and chilled water system piping at 150 psig for six hours.<br />

4. Gas piping at 150 psig for six hours.<br />

5. High pressure air ducts in accordance with SMACNA standards.<br />

6. Plumbing waste and vent piping, 10 ft. of head for 30 minutes.<br />

7. Glycol feed system piping at 100 psig for six hours.<br />

8. Rainwater piping 10 ft. of head for 30 minutes.<br />

All valves and equipment which may be damaged shall not be subjected to the test pressure.<br />

______________________________________________________________________________<br />

SEGO LILY ELEMENTARY SCHOOL CLASSROOM ADDITION March 2, 2009<br />

TESTING 15042-1