3. Locate construction joints not shown on the Drawings so as not to impair the strength<br />

of the structure. Provide keyways at least 1-1/2" deep in walls, slabs, and between<br />

walls and footings.<br />

4. Where load transfer-slip dowel devices are used, install so that one end of each<br />

dowel bar is free to move. Continue reinforcement across construction joints.<br />

5. Do not tool edges of construction joints at interior concrete slabs.<br />

B. Contraction (Control) Joints: Provide contraction (control) joints, sectioning concrete into<br />

areas as shown on Drawings. If not shown, provide joints at 15 feet on center, locating joints<br />

under partitions where possible. Construct contraction joints for a depth equal to at least 1/4<br />

concrete thickness or a minimum of 1".<br />

1. Form contraction joints using powered saws equipped with shatterproof abrasive or<br />

diamond-rimmed blades. Cut joints into hardened concrete as soon as surface will<br />

not be torn, abraded, or otherwise damaged by cutting action.<br />

3.04 INSTALLATION OF EMBEDDED ITEMS<br />

A. General: Set and build into work anchorage devices and other embedded items required for<br />

other work that is attached to, or supported by, cast-in-place concrete. Use setting drawings,<br />

diagrams, instructions, and directions provided by suppliers of items to be attached thereto.<br />

B. Forms for Slabs: Set edge forms bulkheads and intermediate screed strips for slabs to obtain<br />

required elevations and contours in finished surfaces. Provide and secure units to support<br />

screed strips using of strike-off templates or compacting type screeds.<br />

3.05 PREPARATION OF FORM SURFACES<br />

A. Coat contact surfaces of forms with an approved, non-residual form-coating compound<br />

before reinforcement is placed.<br />

B. Do not allow excess form-coating material to accumulate in forms or to come into contact with<br />

in-place concrete surfaces against which fresh concrete will be placed. Apply in compliance<br />

with manufacturer's instructions.<br />

C. Coat steel forms with a non-staining, rust-preventative form oil or otherwise protect against<br />

rusting.<br />

3.06 CONCRETE PLACEMENT<br />

A. Inspection: Before placing concrete, inspect and complete formwork installation, reinforcing<br />

steel and items to be embedded or cast-in. Notify other crafts to permit installation of their<br />

work; cooperate with other trades in setting such work.<br />

B. General: Comply with ACI 304, and as herein specified.<br />

C. Coordinate the installation of joint materials with placement of forms and reinforcing steel.<br />

D. Deposit concrete continuously or in layers of such thickness that no concrete will be placed<br />

on concrete that has hardened sufficiently to cause the formation of seals or planes<br />

of weakness. If a section cannot be placed continuously, provide construction joints as<br />

herein specified. Deposit concrete to avoid segregation at its final location.<br />

E. Placing Concrete in Forms: Deposit concrete in forms in horizontal layers not deeper than<br />

24" and in a manner to avoid inclined construction joints. Where placement consists of<br />

SEGO LILY ELEMENTARY SCHOOL CLASSROOM ADDITION MARCH 2, 2009<br />

CONCRETE WORK 03300 - 8