INSTALLATION OF DUCTS:<br />

All ducts shall be installed in compliance with the latest editions of the SMACNA manuals.<br />

All necessary allowance and provisions shall be made in the installation of sheet metal ducts for the<br />

structural conditions of the building, and ducts shall be transformed or divided as may be required.<br />

Whenever this is necessary, the required area shall be maintained. All changes, however, must be<br />

approved and installed as directed.<br />

Pre-manufactured ducts shall be connected to rigid ducts and equipment with the solid wraps of fabric duct<br />

tape and tyton bands drawn tight to form an airtight joint.<br />

During the installation, the open ends of all ducts shall be protected by covering with plastic sheet tied in<br />

place to prevent debris and dirt from entering.<br />

Install this work in cooperation with other trades so that there will be no delay in progress of construction<br />

work. It is extremely important that the duct system be clean before connections are made to the VAV<br />

boxes.<br />

The contractor shall take special care when running exposed ductwork to insure that the final installation is<br />

neat in appearance.<br />

Spiral ducts running exposed in occupied areas shall be hung with an aircraft cable type hanger.<br />

Under no circumstances shall ductwork be supported from the metal roof deck.<br />

Ceiling outlets shall be rigidly supported from the overhead structure with G.I. wires or straps, or from rigid<br />

galvanized iron ductwork. Outlets shall not be supported from T-bar ceilings or metal roof deck.<br />

Hanger and Supports:<br />

Hangers for ducts up to 18" in width shall be placed on not more than 8'-0" centers. Ducts 19" and over in<br />

width shall be supported on not more than 4'-0" centers. Hangers shall be placed plumb and present a near<br />

appearance. Construct hangers from galvanized band iron 1" x 1/8" for duct up to 36" wide. Hangers shall<br />

extend down the sides of the ducts not less than 9". On ducts less than 9" in depth, hangers shall extend<br />

the full depth of the ducts. Attach hangers to ducts using not less than three rivets or parker screws of<br />

appropriate sizes. It is essential that all ducts be rigidly supported. Where vertical ducts pass thru floors or<br />

roofs, supporting angles shall be rigidly attached to ducts and to the structure. Angles shall be galvanized<br />

and of sufficient size to support the ductwork rigidly. Place supporting angles on at least two sides of the<br />

duct. For round ducts, strap hangers shall extend completely around ducts.<br />

Ceiling outlets shall be rigidly supported from the overhead structure with G.I. wires on straps, or from rigid<br />

galvanized iron ductwork. Outlets shall not be supported from T-bar ceilings unless approved by the<br />

owner's representative.<br />

-<br />

___________________________________________________________________________________<br />

____________<br />

SEGO LILY ELEMENTARY SCHOOL CLASSROOM ADDITION March 2, 2009<br />

AIR DISTRIBUTION 15800 - 14