SPECIAL CONDITIONS<br />

2.01 PERMITS AND SURVEYS<br />

A. The Owner's Authorized Representative shall establish all lot lines and restrictions. All other lines,<br />

grades and levels shall be established by the Contractor and he shall verify all dimensions, lines and<br />

grades indicated on the drawings. The Owner's Authorized Representative shall furnish all surveys.<br />

Permits and licenses required for execution of the work shall be procured and paid for by the<br />

Contractor. The Contractor shall give all notices, call for inspections and comply with all laws and<br />

ordinances bearing on the work.<br />

2.02 SUPERVISION<br />

A. The Contractor shall give sufficient supervision to the work, using best skill and attention. When<br />

absent from job, he will appoint a supervisor capable of discussing minor matters with the Owner's<br />

Authorized Representative. He shall carefully study and compare all drawings, specifications and<br />

other instructions for the work. Any work indicated in a manner which would make it difficult to<br />

produce first class work, or any discrepancies or conflicts which appear between drawings and<br />

specifications and local ordinances or restrictions shall be referred to Owner's Authorized<br />

Representative for interpretation or correction before proceeding with work. Alleged extras shall be<br />

presumed to be part of Contract without additional charge unless certified by Owner's Authorized<br />

Representative.<br />

B. The maintenance foreman on the job shall be a competent English speaking supervisor, experienced<br />

in landscape maintenance and capable of discussing matters on the job site.<br />

C. Workman shall present a neat appearance at all times and shall conduct all work operations and<br />

dealings with the public in a courteous manner. Workman shall be fully clothed at all times.<br />

2.03 GENERAL SITE CONDITIONS<br />

A. Prior to any excavation of the soil, the Contractor shall locate all utilities, cables, conduits, sprinkler<br />

lines, heads, valves, control wires, sewers, septic tanks and such other utilities as are commonly<br />

encountered underground and he shall take proper precaution as not to damage or disturb such<br />

improvements. If a conflict exists between such obstacles and the proposed work, he shall promptly<br />

notify the Owner's Authorized Representative who will arrange for relocation. Contractor will proceed<br />

in the same manner if rock layers or any other condition encountered underground makes changes<br />

advisable.<br />

B. Notify Landscape Architect in writing of soil or drainage conditions encountered during planting<br />

operations which are detrimental to the growth of plant material.<br />

C. The site shall be kept clean and free of excess equipment, materials and rubbish incidental to the<br />

work during the construction and maintenance period.<br />

D. The Contractor shall note all existing finish grades prior to commencing work. Restore finish grades<br />

changed during the course of the work to original contours or intended contours where practical.<br />

2.04 FINAL INSPECTION<br />

A. Upon completion of work in its entirety, Contractor shall notify the Owner's Authorized<br />

Representative who will arrange for final inspection at which time the Contractor shall be present.<br />

Any assumed or existing variance or omission shall be noted at this time, and the Contractor shall<br />

SEGO LILY ELEMENTARY SCHOOL CLASSROOM ADDITION MARCH 2, 2009<br />

LANDSCAPING 02900-2