outed in the ceiling space and not in the concrete slab. For wireless access point locations,<br />

! inch conduit can be utilized.<br />

All conduits will be run from the location in one complete and continuous path to the cable tray<br />

and bonded to the cable tray as per ANSI/TIA/EIA Standards and the National Electric Code.<br />

To be completed by division 16000 contractors. Distance from end of conduit to cable basket<br />

will not exceed 36 inches.<br />

**NOT to have more than 180 degree bend radius in the entire span of the conduit from end to<br />

end. If more bend radius is required, install a 4 gang electrical box after the initial first 180<br />

degrees of bend radius, and continue with this practice through the entire span of the conduit<br />

until the path is installed completely<br />

Each conduit installed by 16000 contractors, shall service only one location each. Each<br />

conduit will have a 200 lb pull string, and grounding bushing and ground wire installed by<br />

division 16000 contractors.<br />

D. Installation shall conform to the following basic guidelines:<br />

1. Cable basket and all transitions will be installed under all of the mechanical<br />

components, and will route to each of the MDF/IDF location. To be completed by<br />

division 16000 contractors.<br />

2. Clear pathways will be provided by division 16000 contractor from within each room,<br />

to the hallway with a solid conduit ran to the location, and bonded to the cable tray for<br />

all locations.<br />

3. All cabling will be run in a cable tray or cable basket as per specified in Section 2.<br />

References above, and according to ANSI/TIA/EIA Standards and the National<br />

Electric Code. To be installed by the division 16000 contractors.<br />

4. All conduits will be run from location and will be bonded to the cable tray directly as<br />

per ANSI/TIA/EIA Standards the National Electric Code as specified above in item d.<br />

To be installed by division 16000 contractors.<br />

5. Use of approved wire, cable, and wiring devices.<br />

6. Neat and uncluttered wire termination.<br />

Termination/Organization of racks is to be as follows:<br />

a. Fiber termination as necessary is to be mounted in a fiber tray in the top 2U<br />

of the Data rack. The first U space is to be utilized for the j-bolt to attach the rack<br />

to the ladder rack supports.<br />

b. 1 Horizontal wire management Part Number # WMBK will be placed on the rear<br />

of each patch panels to support the terminated cables within the patch panel.<br />

c. Data patch panels (48 ports) spaced so that a 1U network device can be placed<br />

in between each termination group of 48 cables.<br />

d. No zip ties to be used for grouping of wires, use Velcro strapping on all.<br />

SEGO LILY ELEMENTARY SCHOOL CLASSROOM ADDITION March 2, 2009<br />

TELEPHONE AND DATA DISTRIBUTION 17000-11