SECTION 15030 - SYSTEM COMMISSIONING<br />

PART 1.00 - GENERAL<br />

DESCRIPTION:<br />

The work required under this section shall include, but not necessarily be limited to, the following:<br />

The pre-startup inspection of all systems by a qualified systems commissioning contractor, and coordination of<br />

subsequent correction of any incorrect items.<br />

Repair, replacement, or adjustment of each item shall be performed by the installing contractor.<br />

System operations inspection.<br />

All personnel used on the job site shall be "Certified Technicians" certified by the National Certification Board for<br />

TAB Technicians, 601 North Fairfax Street, Suite 240, Alexandria, Virginia, 22314, (703) 739-7200, who shall<br />

have been permanent, full-time employees of the firm for a minimum of six (6) months prior to the start of the<br />

work for this project.<br />

The intent of this section is to provide for proper installation, startup, service, and operation of the mechanical<br />

systems in preparation for system balancing. See Section 15043 for balancing.<br />

SITE VISITS:<br />

The system commissioning contractor shall visit the construction site periodically as construction progresses to<br />

insure that the work is being installed in a manner which will insure that the start-up and system commissioning<br />

work will proceed without interruption for remedial work once the system commissioning work is started.<br />

Site status reports shall be submitted to the owner's representative as the work progresses.<br />

A minimum of six (6) pre-commissioning site visits will be required.<br />

PRE-STARTUP INSPECTION:<br />

The pre-startup inspection of all systems shall provide for verifying that each piece of equipment is properly<br />

installed and prepared for startup.<br />

All pertinent items shall be checked, including, but not necessarily limited to, the following:<br />

1. Removal of shipping stops.<br />

2. Vibration isolators and seismic snubbers properly aligned and adjusted.<br />

3. Flexible connections are properly aligned.<br />

4. Belts are properly adjusted.<br />

5. Belt guards and safety shields are in place.<br />

________________________________________________________________________________________________________________________________________________________________________________<br />

_______<br />

SEGO LILY ELEMENTARY SCHOOL CLASSROOM ADDITION March 2, 2009<br />

SYSTEM COMMISSIONING 15030-1