2.03 MATERIALS<br />

A. Special Tools:<br />

1. Provide six of each type of special tool for adjusting and regulating hardware. These<br />

are to be turned over to the Owner upon completion.<br />

B. Templates:<br />

1. Furnish hardware templates to each fabricator of doors, frames, and other work, to be<br />

factory prepared for the installation of hardware. Upon request, check the shop<br />

drawings of such other work to confirm that adequate provisions are made for the<br />

project installation of hardware.<br />

C. Silencers:<br />

1. Provide silencers in all metal door frames unless specified elsewhere to be provided<br />

as part of the door and frame unit, or unless continuous bumper-type weatherstripping<br />

is shown or specified. Provide 3 silencers units in a single door frame and provide 4<br />

silencer units in double door frames. Omit silencers from fire-rated door openings.<br />

PART 3 - EXECUTION<br />

3.01 INSTALLATION<br />

A. Mount hardware units at heights recommended in "Recommended Locations for Builder's<br />

Hardware" by DHI, except as otherwise specifically indicated or required to comply with<br />

governing regulations and except as may be otherwise directed by the Architect.<br />

B. Install each hardware item in compliance with the manufacturer's instructions and<br />

recommendations. Wherever cutting and fitting is required to install hardware onto or into<br />

surfaces which are later to be painted or finished in another way, install each item completely<br />

and then remove and store in a secure place during the finish application. After completion of<br />

the finish application, reinstall each item. Do not install surface-mounted items until finishes<br />

have been completed on the substrate.<br />

C. Set units level, plumb, and true to line and location. Adjust and reinforce the attachment<br />

substrate as necessary for proper installation and operation.<br />

D. Drill and countersink units that are not factory prepared for anchorage fasteners. Space<br />

fasteners and anchors in accordance with industry standards.<br />

E. Knox-Box: Mount in masonry wall at 6 feet above the foundation wall. Install recessed<br />

mounting kit plumb and flush with face of wall. Install with four 3/8” grade 5 or grade 8<br />

fasteners to securely anchor box to wall.<br />

1. Locate Knox-Box at front door as shown on the plans or as directed by Architect.<br />

Confirm location with the local fire department prior to installing.<br />

3.02 ADJUST AND CLEAN<br />

A. Adjust and check each operating item of hardware and each door to ensure proper operation<br />

of function of every unit. Lubricate moving parts with type of lubrication recommended by<br />

manufacturer (graphite type if no other is recommended). Replace units that cannot be<br />

adjusted and lubricated to operate freely and smoothly as intended for the application made.<br />

B. Final adjustment: Wherever hardware installation is made more than 1 month prior to the date<br />

of substantial completion, return to the project and adjust all hardware items.<br />

SEGO LILY ELEMENTARY SCHOOL CLASSROOM ADDITION MARCH 2, 2009<br />

FINISH HARDWARE 08700-3