SECTION 01500 - CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS<br />

PART 1 - GENERAL<br />

1.01 SCOPE<br />

A. The work required under this section consists of all temporary construction and related items<br />

necessary to complete the work indicated within the Contract Documents.<br />

1.02 OFFICE FACILITIES<br />

A. Provide a field office for the duration of the project. This office and its facilities shall be<br />

accessible to the Owner and Architect or their representatives. Field office shall be<br />

appropriately heated and cooled. Provide table to layout drawings and provide sufficient,<br />

accessible filing space for documents.<br />

1.03 TOILET FACILITIES<br />

A. Provide toilet facilities for workmen during the course of construction. Comply with applicable<br />

health codes.<br />

1.04 SCAFFOLDING AND RUNWAYS<br />

A. Provide and maintain for the duration of the work, as required, all scaffolding, hoists, false<br />

work, staging, for performance of the work under this contract, except as may be otherwise<br />

specified in the several specifications sections bound herein.<br />

B. All scaffolding, runways and the like shall comply with the requirements of applicable local,<br />

state and federal statutes, laws and ordinances, including safety rules and regulations of<br />

authorities and insurance carriers having jurisdiction.<br />

1.05 PROTECTION<br />

A. Provide adequate protection for all persons, all parts of work, and all materials furnished for<br />

and installed therein not expressly covered under other sections of these documents.<br />

B. Immediately following the initial delivery and storage of combustible materials at the site of the<br />

work, and throughout the construction period thereafter, supply and maintain suitable and<br />

adequate means of fire protection about flammable structures or grouping of combustible<br />

materials incident to the Work.<br />

C. Maintain all protection media in place and in good order until removal thereof is approved by<br />

Architect or until immediately prior to final inspection of work.<br />

1.06 TEMPORARY ENCLOSURES<br />

A. Provide temporary dust-tight enclosures as required to protect facilities and delivered<br />

materials from weather, thievery, and vandalism.<br />

B. At the end of the day's work, close and secure temporary enclosures.<br />

1.07 DUST ABATEMENT<br />

A. Provide necessary equipment and methods to eliminate dust in all areas of construction and<br />

facility during the entire term of the contract. Excess dirt or materials that are deposited<br />

!<br />

SEGO LILY ELEMENTARY SCHOOL CLASSROOM ADDITION MARCH 2, 2009<br />

CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS 01500-1