Locations: Install thermometers and thermometer wells at the following locations, and elsewhere as<br />

indicated.<br />

1. At the inlet and the outlet of each hydronic zone.<br />

2. At the inlet and the outlet of each hydronic boiler and chiller.<br />

3. At the inlet and the outlet of each hydronic coil in air handling units, and built-up central systems.<br />

4. At the inlet and the outlet of each hydronic heat exchanger.<br />

5. At the inlet and the outlet of each hydronic heat recovery unit.<br />

6. At the inlet and the outlet of each thermal storage tank.<br />

7. Thermometer Wells: Drill and tap pipes 5-inch and larger for installation of wells. Provide tees or<br />

reinforced welding fittings on pipes smaller than 5-inch for installation of wells. Provide oversize<br />

tees or enlarge pipe smaller than 3-inch at points where wells are installed to avoid restriction of<br />

flow.<br />

INSTALLATION OF PRESSURE GAUGES:<br />

General: Install pressure gauges at locations shown on the drawing and where specified.<br />

Locations: Install pressure gauges in the following locations, and elsewhere as indicated.<br />

1. At the suction and the discharge of each pump.<br />

2. At the discharge of each pressure reducing valve.<br />

3. At the water service outlet.<br />

4. At the inlet and the outlet of water-cooled condensers and refrigerant cooled chillers.<br />

Pressure Gauge Cocks: Provide stem mounted pressure gauges with T-handle cocks and pressure<br />

snubbers.<br />

INSTALLATION OF FLOW METERS:<br />

General: Install flow meters at locations shown on the drawings and where specified. Install in accordance<br />

with ASME recommendations for flow meters.<br />

Locations: Install flow meters in the following locations, and elsewhere as indicated.<br />

1. At the discharge of each pump.<br />

2. At the inlet of each hydronic coil in built-up central systems.<br />

Piping: Install piping in the exact locations and arrangement, both upstream and downstream of primary<br />

elements, as required by the manufacturer's published literature. Provide any necessary piping changes<br />

required for certification without additional cost.<br />

Horizontal Pipe: Provide the connection nipples at, or slightly above, the horizontal centerline of the pipe to<br />

minimize the entrance of gases and impurities when flow is measured in horizontal pipe.<br />

Taps: Provide taps with shut-off valves and quick connecting hose fittings for portable meters or<br />

double-ferrule compression fittings for connection to tubing for permanently located meters or recorders.<br />

_____________________________________________________________________________________<br />

_<br />

SEGO LILY ELEMENTARY SCHOOL CLASSROOM ADDTION March 2, 2009<br />

BASIC MATERIALS & METHODS 15050-31