1. Ductile Iron Pipe: Install in accordance with AWWA C600 "standard for installation of<br />

ductile-iron water mains and their appurtenances" and in accordance with instructions<br />

from water purveyor.<br />

2. Copper Tube: Install in accordance with CDA "Copper Tube Handbook".<br />

3. PVC Pressure pipe, PVC pressure fittings, gaskets, and gasketed joints.<br />

B. Depth of Cover: Provide minimum cover over piping of 12" below average local frost depth or<br />

42" below finished grade, whichever is greater.<br />

C. Water Main Connection: Arrange and pay for tap in water main, of size and in location as<br />

indicated, from water Purveyor.<br />

D. Water Service Termination: Terminate potable water piping 5'-0" from building foundation in<br />

location and invert as indicated. Provide temporary pipe plug for piping extension into building.<br />

1. Mark location with surface marker.<br />

3.5 PIPING INSTALLATION<br />

A. General Locations and Arrangements: Drawing plans and details indicate general location and<br />

arrangement of underground water pipes. Location and arrangement of piping layout take<br />

design considerations into account. Install piping as indicated, to extent practical. Where<br />

specific installation is not indicated, follow piping manufacturer's written instructions.<br />

B. Install proper size increasers, reducers, and couplings where different sizes or materials of<br />

pipes and fittings are connected. Reducing size of piping in direction of flow is prohibited.<br />

C. Tunneling: Install pipe under streets or other obstructions that cannot be disturbed by tunneling,<br />

jacking, or a combination of both.<br />

D. Install piping according to the following:<br />

1. Install piping with restrained joints at tee fittings and at horizontal and vertical changes in<br />

direction. Use corrosion-resistant rods, pipe or fitting manufacturer's proprietary restraint<br />

system, or cast-in-place concrete supports or anchors.<br />

2. Install piping with line and grade as indicated or below frost line if not inidcated.<br />

3. Install ductile-iron pressure piping according to AWWA C600 or AWWA M41.<br />

4. Install ductile-iron special fittings according to AWWA C600.<br />

5. Install PVC pressure piping according to AWWA M23 or ASTM D 2774 and<br />

ASTM F 1668.<br />

6. Install PVC water-service piping according to ASTM D 2774 and ASTM F 1668.<br />

3.6 INSTALLATION OF VALVES<br />

A. Install valves with stems pointing up. Provide valve box over underground valves.<br />

3.7 INSTALLATION OF WATER METER AND VAULT<br />

A. Install Water Meter and Vault to comply with City Water Department Standards.<br />

SEGO LILY ELEMENTARY SCHOOL CLASSROOM ADDITION MARCH 2, 2009<br />

WATER UTILITY PIPING 02008 - 6