SUPPLEMENTARY GENERAL CONDITIONS<br />

The supplementary General Conditions contain amendments and additions to the A.I.A. General Conditions.<br />

Where any part of the A.I.A. General conditions is modified or voided by the Supplementary General<br />

Conditions, the unaltered provisions shall remain in effect.<br />

ARTICLE 3 – CONTRACTOR<br />

Under 3.3 “Supervision and <strong>Construction</strong> Procedures, “add the following:<br />

3.3.5 “Owner will establish lot lines, restrictions, and a permanent bench mark. All other grades, lines,<br />

levels, and bench marks shall be established and maintained by the Contractor.”<br />

3.3.6 “Contractor shall provide and maintain well-built batter boards at corners. He shall establish and<br />

safeguard bench marks in at least two widely separated places. As work progresses, he shall<br />

establish exact locations of partitions on rough floors as a guide to the various trades.”<br />

3.3.7 “Contractor shall verify all grades, lines, levels, and dimensions indicated on the drawings, and shall<br />

report all inconsistencies to the Architect before commencing work.”<br />

Under 3.5, “Warranty,” add the following:<br />

3.5.2 “The Contractor shall guarantee his work of the entire project for a period of one year after date of<br />

substantial completion unless otherwise required. He shall at his own expense, replace or adjust<br />

any of his work which may require it during that time, and he shall pay for all repair or replacement<br />

or other work occasioned by such operation.”<br />

3.5.3 “If within one year after the Date of Substantial Completion or within such longer period of time as<br />

may be prescribed by law or by the terms of any applicable special guarantee required by the<br />

Contract Documents, any of the work is found to be defective or not in accordance with the<br />

Contract Documents, the Contractor shall correct it promptly after receipt of written notice from the<br />

Owner to do so, unless the Owner has previously given the Contractor a written acceptance of such<br />

condition. The Owner shall give such notice promptly after discovery of the condition.”<br />

Under 3.18 “Indemnification,” add the following:<br />

3.18.4 “Indemnities” shall be defined for the purposes of their Article:<br />

Alpine School District and while acting within the scope of their duties as such: Any member of<br />

its Board of Education or advisory committees, or any of its elected or appointed officials, or<br />

any of its employees or authorized volunteers, and the Architect or his representative.”<br />

ARTICLE 4 – ADMINISTRATION OF THE CONTRACT:<br />

Under 4.7 “Claims and Disputes,” add the following:<br />

4.7.10 The owner will not be responsible for expenses incurred during delays on the project, if any.<br />

ARTICLE 7 – CHANGES IN THE WORK:<br />

Under 7.2 “Change Orders,” add the following:<br />

7.2.3 In addition, if the proposal includes a time extension, a justification therefore shall also be furnished.<br />

The proposal, together with the price breakdown and time extension justification, shall be furnished<br />

within thirty (30) days of the date first requested by the Architect.<br />

SEGO LILY ELEMENTARY SCHOOL CLASSROOM ADDITION MARCH 2, 2009<br />

SUPPLEMENTARY GENERAL CONDITIONS 00800-1