D. Label cables, outlets, patch panels, backbones, and punch blocks with closet letter rack,<br />

patch panel and port IE A 1-2-23.<br />

E. Marked floor plans showing outlet locations, type, and cables shall be delivered to the owner<br />

two (2) weeks prior to move in to allow the owner's personnel to connect and test ownerprovided<br />

equipment in a timely fashion.<br />

F. Two (2) sets of as-built drawing shall be delivered to the owner (District Technology<br />

Department) within four (4) weeks of acceptance of project by the owner. A set of as-built<br />

drawings shall be provided to the owner in media form (CD ROM or 3.5" floppy disks) and<br />

utilizing CAD software that is acceptable to the owner. Contractor is to deliver to the owner<br />

(Technology Department of District) within six (6) weeks of acceptance of project by owner.<br />

3.4 TESTING<br />

A. Testing shall conform to TIA/EIA 568B. Testing shall be accomplished using level III field<br />

testers.<br />

B. Test each pair and shield of each cable for opens, shorts, grounds, and pair reversal. Correct<br />

grounded and reversed pairs and examine open and shorted pairs to determine if problem is<br />

caused by improper termination. If termination is proper, tag bad pairs at both ends and note<br />

on termination sheets.<br />

1. Perform testing of copper cables with tester meeting TIA/EIA 568B requirements.<br />

2. If fiber/copper backbone cable contains more than one (1) percent bad pairs, remove<br />

and replace entire cable.<br />

3. If horizontal cable contains more than one (1) percent bad conductors, remove and<br />

replace span of cable entirely.<br />

C. Initially test optical cable with a light source and power meter-utilizing procedures as stated in<br />

ANSI/TIA/EIA- 526-14A. If loss tests results are outside acceptable range, test cable with<br />

optical time domain reflectometer to determine cause of variation. Correct improper<br />

terminations and replace damaged cables at no additional charge to the owner or location.<br />

END OF SECTION 17000<br />

1. Cables shall be tested at 850 nm and 1300 nm for multimode optical fiber cables.<br />

2. Testing procedures shall utilize "Method A" - one jumper references.<br />

3. Testing will be performed with the most recent version of software as required by<br />

Siemon to ensure warranty compliance.<br />

SEGO LILY ELEMENTARY SCHOOL CLASSROOM ADDITION March 2, 2009<br />

TELEPHONE AND DATA DISTRIBUTION 17000-13