planting.<br />

F. Immediately after planting, stake all trees to prevent damage from wind. Install Guy wires only as<br />

needed on larger trees. Refer to tree staking and guying details and submit prices for each.<br />

G. Prepare raised earth basin as wide as ball at each plant for watering prior to ground cover and lawn<br />

installation.<br />

H. Grade areas around plants, to finish grade and dispose of excess soil.<br />

I. Watering - immediately after planting, water shall be applied to each tree and shrub, in such a<br />

manner as not to disturb backfill, and to the extent that all materials in the planting hole are<br />

thoroughly saturated.<br />

J. Before any plants are planted, all planted areas are to have been graded in an acceptable manner to<br />

assure positive drainage.<br />

K. All box trees shall be pre-selected by Landscape Architect when deemed necessary to insure quality.<br />

L. All 1,5, and 15-gallon trees shall be staked per detail. 20" box trees and larger are to be either<br />

staked or guyed as necessary or as specified by Landscape Architect.<br />

M. Contractor shall be responsible for stockpiling (by nursery) of tree boxes and insuring they are<br />

returned to suppliers in good condition. Contractor shall notify nurseries for pick-up.<br />

N. Contractor shall be responsible for maintaining all planting until final inspection and approval by<br />

Landscape Architect and turn over to the Owner's Authorized Representative.<br />

O. If required, Contractor shall submit with bid unit prices for all landscape materials (should be installed<br />

prices).<br />

P. Contractor shall verify location of all underground utilities and services prior to any digging.<br />

Contractor assumes full responsibility for all damage caused by failure to do so.<br />

Q. All plant material shall be spotted by Contractor and approved on site by Landscape Architect, prior<br />

to digging pits, when determined necessary.<br />

R. Refer to landscape plan and detail for method of separating all shrub/ground cover areas from lawn<br />

areas.<br />

S. Where circumstances permit, plant shrubs a minimum of 30" from all landscape light fixtures.<br />

T. Where circumstances permit, plant no specimen tree closer than five (5) feet to edge of paving,<br />

headerboard or roof line. Deep root devices are recommended for any specimen trees planted<br />

closer than ten (10) feet or palms planted closer than four (4) feet to any hardscape, walls or<br />

building. Use per method specified on "Root Barrier" detail. Consult Landscape Architect prior to<br />

planting.<br />

U. Where circumstances permit, plant no shrub closer than eighteen (18) inches to an edge of paving or<br />

headerboard.<br />

V. All vines and espaliers to be removed from stake or trellis and fastened to walls with fastening<br />

method described in the planting notes.<br />

W. Provide all shrubs which need support with !" square redwood stakes. Once installed, trim top of<br />

SEGO LILY ELEMENTARY SCHOOL CLASSROOM ADDITION MARCH 2, 2009<br />