SECTION 00500 – PROJECT SCHEDULES<br />

PART 1 - GENERAL<br />

1.01 SUMMARY<br />

A. Refer to the following Preliminary <strong>Construction</strong> Schedule for tentative dates of when work will<br />

be expected to be completed. (Schedule will be issued via addendum.)<br />

B. Refer to the Schedule of Responsibility for Temporary Facilities and General Conditions<br />

Services for subcontractor requirements with respect to the services indicated.<br />

1.02 SCHEDULE OF RESPONSIBILITY FOR TEMPORARY<br />

FACILITIES AND GENERAL CONDITIONS SERVICES<br />

Note: “…as required” means by the contract documents, or required by regulations, or required in order to<br />

execute the Subcontractor’s work, or reasonably required of the Subcontractor by the General Contractor.<br />

DESCRIPTION PROVIDED, MAINTAINED & REMOVED BY<br />

1. Temporary Fencing Site Fencing Contractor<br />

2. Drinking Water Each Subcontractor<br />

3. Additional temporary power drop Electrical Subcontractor<br />

(connect & disconnect) distribution<br />

System and panels per Section<br />

01500<br />

4. Temporary Power Electrical Subcontractor<br />

5. Temporary Interior Lighting per Access Lighting by GC<br />

Section 01500 and Utah OSHA Task Lighting by each trade<br />

6. Temporary Task Lighting beyond Each Subcontractor, as required by their work<br />

The requirements of Section 01500<br />

And Utah OSHA<br />

7. Two (2) each Temporary Freeze- Mechanical Subcontractor<br />

Proof Hose Bibs at Ground Level<br />

8. Temporary Fire Extinguisher General Contractor for his field office, and each<br />

Subcontractor as needed<br />

9. Temporary Roof Access Each Subcontractor, as required for their work<br />

10. Safety Barricades, Methods and Each Subcontractor as required; for example,<br />

Equipment as required by Utah perimeter rails at the roof (if required) shall be by<br />

OSHA except as noted otherwise the Roofing Subcontractor, and barricades or<br />

herein closures required at a floor penetration for duct-<br />

work shall be by the Mechanical Subcontractor.<br />

11. Site Dust Control Subcontractor during Demolition Operations<br />

SEGO LILY ELEMENTARY SCHOOL CLASSROOM ADDITION MARCH 2, 2009<br />

PROJECT SCHEDULES 00500 - 1