5. The starter shall have fault isolation, to automatically disconnect the power supply to<br />

protect the motor in the event of a semi-conductor fault.<br />

6. The starter shall be equipped with an Electronic Timing Relay, adjustable from 0.1 to<br />

60 seconds, to delay the start of the motor.<br />

7. Provide an elapsed Time Meter on door to indicate pump run time.<br />

D. Finish: Fronts shall be made of cleaned phosphatized steel with rust-inhibiting primer and<br />

electro-deposited baked enamel finish, manufacturer's standard color.<br />

PART 3 - EXECUTION<br />

3.1 INSTALLATION:<br />

A. Motor Controllers and Starters shall be installed level, plumb and anchored to the mounting<br />

surface in accordance with the manufacturer's instructions. The equipment shall be protected<br />

if stored during construction.<br />

B. Seismic restraints: Provide anchor bolts, angle irons and fasteners to attach the combination<br />

starters rigidly to the building structure per IBC seismic requirements.<br />

C. Inspect operating mechanisms for malfunctioning and, where necessary, adjust units for free<br />

mechanical movement.<br />

D. Touch-up scratched or marred surfaces to match original finish.<br />

E. Clean interiors of motor controllers and starters prior to energization.<br />

3.2 TESTING:<br />

A. When all motors are connected and the pre-energizing tests have been completed, the<br />

contractor shall operate the equipment to demonstrate that all control equipment and<br />

overcurrent protective devices perform as specified. Any deficiencies found shall be<br />

corrected and tests repeated. All test results and dates shall be recorded and submitted to<br />

the Engineer and the Owner's Representative with statement certifying that the equipment is<br />

safe and ready for use.<br />

END OF SECTION<br />

SEGO LILY ELEMENTARY SCHOOL CLASSROOM ADDITION March 2, 2009<br />

MOTOR CONTROLLERS Section 16475-3