1. Comply with installation instructions of U.S.G. installation handbook, latest edition.<br />

2. Install additional stud and jambs of openings.<br />

3. Install deflection tracks where studs are continuous to roof deck.<br />

C. Gypsum Board:<br />

1. Apply boards with long dimension perpendicular to framing members with all abutting<br />

ends and edges over supports. Neatly fit and stagger all end joints. Make joints occur<br />

on different studs at opposite sides of partition. Cut and fit neatly around all outlets<br />

and switches. Space fasteners 8" o.c. along vertical edges and 12" o.c. at midpoints,<br />

3/8" from edge of board. Fasten boards to backings specified.<br />

2. Erection techniques shall result in plumb and straight surfaces with no waves or<br />

buckles, free or unevenness at joints.<br />

3. Joints shall be in continuous moderate contact.<br />

4. If framing members are out of alignment, bowed or warped, correct to make true<br />

surfaces before application of gypsum board. Use method of correction approved by<br />

the Architect. Make finished walls or ceilings plumb and level without ridges, bows, or<br />

warps.<br />

5. Execute wallboard work when building temperature is within a range of 55 degrees to<br />

90 degrees F. Ventilate to eliminate excessive moisture.<br />

D. Fiberglass-Mat Faced Gypsum Backing Board:<br />

1. General: In accordance with ASTM C840 and the manufacturer’s recommendations.<br />

Install at toilet room walls.<br />

a. Install other accessories where required.<br />

E. Finishing Gypsum Board Assemblies<br />

1. General: Apply joint treatment at gypsum board joints (both directions); flanges of<br />

corner beads, edge trim, and control joints; penetrations; fastener heads, surface<br />

defects, and elsewhere as required to prepare gypsum board surfaces for decorations<br />

and levels of gypsum board finish indicated.<br />

2. Prefill open joints, rounded or beveled edges, and damaged areas using setting-type<br />

joint compound.<br />

3. Apply joint tape over gypsum board joints except those with trim accessories having<br />

concealed face flanges not requiring taping to prevent cracks from developing in joint<br />

treatment at flange edges.<br />

4. Levels of Gypsum Board Finish: Provide the following levels of gypsum board finish<br />

per GA-214.<br />

5. For gypsum board surfaces exposed to view, provide level 4 gypsum board finish.<br />

Embed tape in joint compound and apply three separate coats of joint compound over<br />

joints, angles, fastener heads, and accessories. Touch up and sand between coats<br />

and after last coat as needed to produce a surface free of visual defects and ready for<br />

decoration. Use one of the following joint compound combinations:<br />

a. Fill (Second) Coat: Job-mixed, drying-type topping compound.<br />

b. Finish (Third) Coat: Job-mixed, drying-type topping compound.<br />

c. Embedding and First Coat: Job-mixed, drying-type all-purpose compound.<br />

d. Fill (Second) Coat: Job-mixed, drying-type all-pourpose compound.<br />

e. Finish (Third) Coat: Job-mixed, drying-type all-purpose compound.<br />

f. Embedding and First Coat: Setting-type compound.<br />

g. Finish (Third) Coat: Job-mixed, drying-type all-purpose compound.<br />

6. For gypsum board not exposed to view (above ceilings), provide a level 2 finish,<br />

applying joint compound for an embedding coat and for a first coat.<br />

7 Allow compound to thoroughly dry for at least 24 hours.<br />

8. Gypsum Wallboard is to be a smooth non-textured finish.<br />

9. Give all dimples at fastener heads and all marred spots on surface of board 1 coat<br />

joint compound and 2 coats finishing compound, applied as each coat is applied.<br />

SEGO LILY ELEMENTARY SCHOOL CLASSROOM ADDITION MARCH 2, 2009<br />

GYPSUM BOARD ASSEMBLIES 09250-4