SECTION 02050 – SELECTIVE DEMOLITION<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Section includes requirements for demolition work.<br />

1. Verify existing utilities to be removed as well as site features to be demolished with<br />

Architect.<br />

B. Demolition includes, but is not limited to, the removal of the following items within the demolition<br />

limit lines:<br />

1. Bearing and non-bearing masonry and metal framed walls.<br />

2. Floor finishes.<br />

3. Ceilings systems.<br />

4. Cabinets.<br />

5. Other interior finishes.<br />

6. Interior doors and windows.<br />

C. Related Sections<br />

1. Division 15: Mechanical and plumbing systems and equipment as indicated on drawings,<br />

including but not limited to fixtures and plumbing in toilet rooms and break room,<br />

abandoned waste/vent lines, abandoned ductwork and underslab ductwork.<br />

2. Division 16: Lighting and electrical systems as indicated on the drawings. Existing light<br />

fixtures may be used for temporary lighting.<br />

D. Drawings and general provisions of contract, including general and supplementary conditions<br />

apply to work in this section.<br />

1.2 SUBMITTALS<br />

A. Schedule: Submit proposed methods and operations of demolition to review prior to start of work.<br />

Include in schedule coordination for shut-off, capping, and continuation of utility services as<br />

required.<br />

B. Explosives: The use of explosives is not permitted without approval from the owner and local<br />

authorities having jurisdiction. Contractor is responsible to obtain all required permits at<br />

contractor’s expense.<br />

C. Traffic: Conduct demolition operations and removal of debris to ensure minimum interference<br />

with roads, streets, walks, and other adjacent occupied or used facilities.<br />

1. Do not close or obstruct streets, walks or other occupied or used facilities without<br />

permission from authorities having jurisdiction. Provide alternate routes around closed or<br />

obstructed traffic ways if required by governing regulation.<br />

D. Protections: Ensure safe passage of persons around area of demolition. Conduct operations to<br />

prevent injury to adjacent buildings, structures, other facilities, and persons.<br />

1. Erect temporary covered passageways as required by authorities having jurisdiction.<br />

2. Provide interior and exterior shoring, bracing, or support to prevent movement,<br />

settlement or collapse of structures to be demolished and adjacent facilities to remain.<br />

SEGO LILY ELEMENTARY SCHOOL CLASSROOM ADDITION MARCH 2, 2009<br />

DEMOLITION 02050 - 1