or partitions are indicated to support fixtures, equipment, services, casework, heavy trim and<br />

furnishings, and similar work requiring attachment to the wall or partition. Where type of<br />

supplementary support is not otherwise indicated, comply with stud manufacturer's<br />

recommendations and industry standards in each case, considering weight or loading<br />

resulting from item supported.<br />

G. Frame wall openings larger than 2'-0" square with double studs, of gauge indicated, at each<br />

jamb of frame except where more than 2 are either shown or indicated in manufacturer's<br />

instructions. Install runner tracks and jack studs above and below wall openings. Anchor<br />

tracks to jamb studs with stud shoes or by welding, and space jack studs same as full-height<br />

studs of wall. Secure stud system wall opening frame in manner indicated.<br />

H. Frame both sides of expansion and control joints, with separate studs; do not bridge the joint<br />

with components of stud system.<br />

I. Install horizontal stiffeners in stud system, spaced (vertical distance) at not more than 4'-6"<br />

o.c. Weld at each intersection.<br />

J. Erection Tolerances: Bolt or weld wall panels (at both horizontal and vertical junctures) to<br />

produce flush, even, true to line joints.<br />

1. Maximum variation in plane and true position between prefabricated assemblies<br />

should not exceed 1/16 inch.<br />

K. Field Painting: Touch-up shop-applied protective coatings damaged during handling and<br />

installation. Use compatible primer for prime coated surfaces; use galvanizing repair paint for<br />

galvanized surfaces.<br />

3.02 SHEATHING, INSTALLATION<br />

A. Preparation:<br />

1. Examine subframing and verify that surface of framing and furring members to<br />

receive sheathing does not vary more than 1/4" from the place of faces of adjacent<br />

members.<br />

B. Install sheathing in accordance with manufacturer’s instructions and applicable instructions in<br />

GA-253 and ASTM C 1280.<br />

1. Install Dens-Glass Gold sheathing with gold side out.<br />

2. Use maximum lengths possible to minimize number of joints.<br />

3. Attach sheathing to metal framing with screws spaced 8" o.c. at perimeter where<br />

there are framing supports; and 8" o.c. along intermediate framing in field.<br />

4. Drive fasteners to bear tight against and flush with surface of sheathing. Do not<br />

countersink.<br />

5. Locate fasteners minimum 3/8 inches from edges and ends of sheathing panels.<br />

6. Building paper: Install building paper or equal with flashing around openings.<br />

C. Finishing:<br />

1. Seal fasteners with sealant.<br />

2. Finish joints with sealant. Reinforce with 2" wide 10 x 10 glass mesh tape.<br />

D. Painted Ceilings and Soffits:<br />

1. Joint treatment and finish preparation:<br />

a. Apply joint tape over joints and embed in setting-type joint compound<br />

specified.<br />

SEGO LILY ELEMENTARY SCHOOL CLASSROOM ADDITION MARCH 2, 2009<br />

COLD-FORMED METAL FRAMING 05400 - 5