Wolfgang Cronenbroeck<br />

It is defi nitely recommended in practice to cleanly separate effort into person-days (PT) <strong>and</strong> du-<br />

ration in time units (e.g. in days).<br />

No. Process estimated effort (PT) number <strong>of</strong> employees Duration (T)<br />

1 Work packet 27<br />

1.1 Create a specifi cations document 5 1 5<br />

1.2 Produce a surface prototype 6 1 6<br />

1.3 Create a model 16 2 8<br />

Classifi cation relationships<br />

Figure 21 | Procedural duration for the three individual procedures from Fig. 20<br />

The following types <strong>of</strong> interdependencies are possible:<br />

– Normal sequence<br />

The previous procedure must be completed before the follow-on procedure begins.<br />

– Beginning sequence<br />

The procedures have the same start time.<br />

– Ending sequence<br />

The procedures have the same ending time.<br />

Fig. 22 shows that the procedures create a specifi cations document <strong>and</strong> create a model must fi rst<br />

be completed before the surface prototype procedure can be started<br />

Scheduling<br />

Figure 22 | Dependencies for the three individual procedures from Fig. 21<br />

Scheduling takes place by setting the start date for the fi rst procedure (1.3.1).<br />

216