217 Project Management<br />

No. PSP code Procedure<br />

name<br />

4 1.3 Work<br />

packet1<br />

5 1.3.1 Create<br />

specifi cations<br />

6 1.3.2 Create<br />

OOA<br />

model<br />

7 1.3.3 Create<br />

surface<br />

prototype<br />

Visualization<br />

Duration Start End PSP code<br />

from previous<br />

14 days Th 26 Apr<br />

07<br />

Th May 15<br />

previous Resource<br />

5 days Th 26 Apr We 2 May Employee<br />

1<br />

6 days Th 26 Apr Th 3 May 1.3.1 (AA) 5AA Employee<br />

2<br />

8 days Fr 4 May Th 15 May 1.3.1, 1.3.2 5; 6 Employee<br />

2<br />

Figure 23 | Scheduling <strong>of</strong> the three individual procedures from Fig. 21<br />

PM s<strong>of</strong>tware is usually used in order to visualize the course plan <strong>and</strong> scheduling.<br />

Figure 24 | Visualization <strong>of</strong> the three individual procedures from Fig. 21<br />

The outcome <strong>of</strong> course planning <strong>and</strong> scheduling is usually a column schedule (Gantt Chart). This<br />

plan is constructed in accordance with the project breakdown <strong>and</strong> contains all project sections, work<br />

packets, individual procedures <strong>and</strong> dependencies. Further on, the defi ned milestones are integrat-<br />

ed into the Gantt Chart <strong>and</strong>, if applicable, the project phases. The scheduling <strong>of</strong> all activities follows<br />

in which the milestone Project Start (PSP code 1.1) is set. The critical path can be determined from<br />

the schedule. This shows that all procedures on the critical path have no buffer, <strong>and</strong> a change in the<br />

duration <strong>of</strong> these procedures has an immediate effect on the date <strong>of</strong> the end <strong>of</strong> the project.<br />

Figure 25 | Schedule