Analysis of Up-ending Jacket Platform during Installation<br />

Chin Jia Chun<br />

Supervisor: Assoc. Prof. Ir. Dr. Eng Ahmad Fitriadhy<br />

Bachelor of Applied Science (Maritime Technology)<br />

School of Ocean Engineering<br />

Universiti Malaysia Terengganu<br />

Steel-structured Jacket Platforms have been extensively installed in Malaysia offshore<br />

oil and gas fields. Prediction of launching and up-ending process are vital to avoid<br />

accidents during installation of such expensive product. To achieve the objective, the<br />

final year project presents numerical simulation of launching and up-ending of Jacket<br />

Platform in waves using Moses. Two up-ending conditions of Jacket Platform have<br />

been taken into account after its launching and lifting by a crane. Several parameters<br />

such as trim angle of the barge, wavelengths, wave directions and number of hooks<br />

during lifting have been considered in the simulation. The numerical results revealed<br />

that an increase of trim angle had led to an increase in launching speed and tipping<br />

time but the up-ending speed of jacket will become slower. Two hook method can<br />

enhance the stability of the Jacket Platform compare to one hook method. It is<br />

generally conclude that decrease of trim angle can result in slower launching process<br />

but faster and safer up-ending process.<br />

209 | U M T U N D E R G R A D U A T E R E S E A R C H D A Y 2 0 1 9