Table 485: CPE Loopback Jack Test (#1212) 2 of 3<br />

Error<br />

Code<br />

Test<br />

Result<br />

Description / Recommendation<br />

CPE Loopback Jack Test (#1212)<br />

1039 ABORT The DS1 Interface circuit pack is providing timing for the system.<br />

Executing this <strong>test</strong> could cause major system disruption. If the DS1<br />

Interface circuit pack needs to be <strong>test</strong>ed, set the synchronization<br />

reference to another DS1 Interface circuit pack or to the Tone-Clock<br />

circuit with the following comm<strong>and</strong> sequence:<br />

1. disable synchronization-switch.<br />

2. set synchronization location.<br />

3. enable synchronization-switch.<br />

1950 ABORT Another loopback/span <strong>test</strong> is already executing on the DS1 board or the<br />

board is in a network requested loopback mode (Line loopback or Payload<br />

loopback). The <strong>error</strong> log will indicate whether a Customer loopback jack<br />

<strong>test</strong>, Far CSU Loopback <strong>test</strong>, or the One-Way Span <strong>test</strong> is executing or if<br />

the board is in line loopback or payload loopback mode. Only one<br />

long-duration loopback/span <strong>test</strong> can be active at a given time.<br />

If a loopback/span <strong>test</strong> is already active, that <strong>test</strong> must be deactivated via<br />

<strong>test</strong> ds1-loop location end-loopback/span-<strong>test</strong> in order to<br />

run this <strong>test</strong>.<br />

2000 ABORT Response to the <strong>test</strong> was not received within the allowed time.<br />

1. Check for board hyperactivity. See Hyperactive DS1/UDS1<br />

Interface Circuit Pack/Media Module.<br />

2100 ABORT Could not allocate the necessary system resources to run this <strong>test</strong>.<br />

1. Retry the comm<strong>and</strong> at 1-minute intervals up to 5 times.<br />

2 FAIL The CLJ-LB <strong>test</strong> failed because it was not set up properly. The DS1<br />

interface pack could not successfully put the CPE loopback jack into<br />

loopback mode.<br />

1. Enter <strong>test</strong> ds1-loop location<br />

cpe-loopback-jack-<strong>test</strong>-begin.<br />

2. If the <strong>test</strong> continues to fail, the problem could be with the DS1<br />

board, the CPE loopback jack equipment, or somewhere between.<br />

Run <strong>test</strong> ds1-loop location ds1/csu-loopback-<strong>test</strong>s<br />

to determine if the loopback <strong>test</strong>s that are closer to the DS1 board<br />

are successful. If any of the <strong>test</strong>s fail, follow the maintenance<br />

strategy that is associated with the failing <strong>test</strong>.<br />